Getting ready to dig!
![](http://photo.blogpressapp.com/photos/12/07/31/s_4005.jpg)
July 12-- dug our basement
![](http://photo.blogpressapp.com/photos/12/07/31/s_4006.jpg)
July 16--poured the footer
![](http://photo.blogpressapp.com/photos/12/07/31/s_4007.jpg)
July 17---set basement walls
![](http://photo.blogpressapp.com/photos/12/07/31/s_4008.jpg)
July 18--took off wall forms
![](http://photo.blogpressapp.com/photos/12/07/31/s_4009.jpg)
July 19--added plumbing
![](http://photo.blogpressapp.com/photos/12/07/31/s_4010.jpg)
July 23--waterproofed basement
![](http://photo.blogpressapp.com/photos/12/07/31/s_4011.jpg)
July 25-- backfilled the basement walls
![](http://photo.blogpressapp.com/photos/12/07/31/s_4012.jpg)
More back filling
![](http://photo.blogpressapp.com/photos/12/07/31/s_4013.jpg)
July 30--prepping the gravel for concrete
![](http://photo.blogpressapp.com/photos/12/07/31/s_4014.jpg)
July 31--I beams placed and concrete poured in
Basement and garage!
![](http://photo.blogpressapp.com/photos/12/07/31/s_4015.jpg)
You see all the wood starting to pile up in front of our house? As far as I know, the next step is FRAMING!!!!! Then there will be an actual physical skeleton of a house I can see!!!!!